Home/Method notes/The battery connection queue

Method note · measured

The battery connection queue

What it measures

What developers asked grid operators to connect, what the operators promised, and what runs today, each as battery power in gigawatts.

Inputs

  • The regulator's annual monitoring query of grid operators, published on SMARD: requests and commitments for battery connections, by calendar year, all voltage levels from medium voltage up, copied by hand once a year
  • The large-battery segment of the register fleet (the battery fleet from the register note), read at its extract date

Method and weighting

Requests and commitments are the figures grid operators report to the regulator. They are copied from the published article into a curated file with the article's address and date, and no figure is recomputed, so a published total stays as published even where its rows sum to a slightly different value.

The running fleet is the large-battery segment of the register fleet at its extract date. The page draws the three counts as bars on one axis in gigawatts and names each bar's own scope beneath it. It states no rate that turns a request into a battery.

Window

Requests are those received in the calendar year shown on the view. Commitments cover all years up to the article's date. The running fleet is the register as downloaded on the date stated on the view. The file is reviewed once a year. Data last refreshed on .

Known limits

  • Developers file the same project with several grid operators, so the requested total counts projects more than once.
  • Commitments include requests from earlier years, so they do not divide into the requests of one year.

Used on

Sources: SMARD, MaStR. Each is described on the Data sources page.